Desalination is now an electricity problem

The marginal cubic metre of desalinated water is an electricity decision, and a grantor that tenders water without locking in power is short the power market for 25 years.

four minute readwater economicsgovernance

Electricity consumption for desalination has doubled since 2010, according to the International Energy Agency’s 2026 commentary on the electrification of the industry. The Middle East and North Africa now hosts over 40 per cent of global capacity, with the Gulf alone accounting for a third.

Underneath those numbers, something has changed. Reverse osmosis has displaced thermal desalination as the dominant technology for new plants.

The marginal cubic metre of extra water is no longer a heat decision. It is an electricity decision.

Capital cost per cubic metre of capacity has fallen with each procurement round. Operating cost, dominated by electricity, now determines whether a project breaks even over its life.

The binding constraint on national water security has shifted from membrane technology to power supply and price. Procurement strategy in most jurisdictions has not caught up.

Most water strategies still read as supply-augmentation documents. The underlying economics have become energy-system documents.

Singapore, which has run reverse osmosis at scale longer than almost any other jurisdiction, reports a stated energy intensity of roughly 3.5 kWh per cubic metre. The European Environment Agency’s 2024 assessment found that water scarcity now affects a widespread portion of European territory.

The convergence of energy-intensive supply and worsening scarcity has produced near-identical procurement responses in jurisdictions that otherwise share little policy DNA.

Morocco announced on December 4 2025 that it intends to source 60 per cent of drinking water from desalination by 2030, up from 25 per cent, with 1.7bn cubic metres a year of new capacity planned. The headlines treated it as a water-security commitment.

It is also a commitment to tripling electricity demand for water supply within five years. The procurement architecture for that electricity has not yet been disclosed.

Algeria’s published targets follow the same pattern. Government disclosures point to 3.7mn cubic metres a day of desalination production reached by the end of 2024, with a target of 5.6mn cubic metres a day by 2030.

The accompanying power generation strategy has been published, by a separate ministry, on a separate timetable.

Saudi Arabia’s Saudi Water Partnership Company seven-year statement for 2024 to 2030 is the sharpest illustration of the gap, because it does more than most. It aims for 100 per cent private participation in desalinated water production by 2030, with bankable power offtake structures embedded in individual projects.

A utility that builds capacity without locking in power offtake terms is short the electricity market for the asset’s life, often 25 years or longer. As Warren Buffett observed, you only find out who has been swimming naked when the tide goes out.

Most water ministries continue to buy capacity as though power were a footnote rather than the binding constraint. It does not require any individual minister to be mistaken.

The gap persists because of how governments are organised. Water ministries and energy ministries report through different cabinet lines, and water purchase agreements and power purchase agreements sit in different legal frameworks.

The structural separation is the explanation. Negligence is not.

The gap is closable through three moves: explicit energy-cost pass-through in long-term water concessions, integrated power-water tendering for new capacity, and disclosed assumptions on grid carbon intensity over the concession term.

None is novel in either sector. They are not yet routine where the two sectors meet.

What is missing is the institutional habit of treating water and power as a single procurement problem rather than two adjacent ones.

Spain’s 2024 Strategic Plan for Water and Climate Adaptation treats desalination as part of the climate toolkit, but implementation responsibility for power procurement sits with autonomous communities and basin authorities rather than the water ministry. The institutional gap is visible in the architecture itself.

England’s regulatory framework places integration responsibility on individual water companies under Ofwat’s price-control regime, with December 19 2024 final determinations pricing energy as an operating cost, not a strategic variable. The gap is embedded in the regulatory accounting.

Civil-law autonomous communities, common-law independent regulation, Gulf concession models: the binding constraint exists across all regulatory traditions. No single institutional fix solves it.

The problem is conceptual, not jurisdictional. The next round of national water strategies should price grid-decarbonisation pathways into the offtake rather than assume them away.

The next regulatory reviews should treat energy as a strategic variable rather than a pass-through. None of that is technically difficult.

Sheikh Zaki Yamani is said to have observed that the stone age did not end for lack of stones. The desalination era will not end for lack of seawater.

But it could end for lack of affordable, reliable, low-carbon power. The next decade of water security will be influenced by the power markets, not the membrane factories.

The takeaway

Three questions for a board

  1. 1Is the power offtake for this plant contracted for the life of the water concession, and on what index?
  2. 2Which ministry owns the power assumption in our water business case, and when did they last sign it?
  3. 3What grid carbon intensity does the concession assume over its term, and is it disclosed?

Kashif

I write on governance, capital and reform in healthcare, water and infrastructure, for boards and investors.

The views are my own and not those of any past or current employer.