Saying ta-ra to PFI but stuck with the hangover

Britain stopped signing PFI contracts in 2018 and will pay for them until the 2040s; the lesson is that the grant was written for the signing, not for the 30 years that followed.

three minute readcapital allocationgovernance

Britain stopped signing Private Finance Initiative contracts in 2018 and will be paying for the ones it signed until the 2040s. The lesson is not that private finance for public buildings fails; it is that the grant was written for the signing and not for the 30 years that followed.

The scale is worth stating plainly. The Infrastructure and Projects Authority's 2022 guidance counts more than 550 PFI contracts still running in England, built for £46bn of capital and committed to £244bn of unitary charges, half of which was still to be paid.

PFI did what it was asked to do. Hospitals and schools were built on time and to a price, maintained to a standard the public sector had rarely funded for itself, and the risk of a leaking roof sat with the company that had built it.

Where it went wrong was in the terms the grantor accepted. The charges were indexed and fixed for decades, the contracts were hard to change when the service changed, and the cost of the private capital was compared with a public option that was never honestly priced.

Those are faults of the grant, and each had a remedy available at signature. A value-for-money test that priced the works with and without private finance, a change mechanism with a known cost, and a cap on the refinancing gains that flowed to equity would have changed the arithmetic of the next 30 years.

The hangover is the expiry. The Commons Public Accounts Committee found in 2021 that more than 200 contracts, with assets worth more than £10bn, end within 10 years, and the authority's leverage falls away before the end, because once the contract closes the remaining cash goes to shareholders and money owed for rectification is almost impossible to recover.

The committee's figures on readiness are the real indictment. The central PFI team stood at 17 people for 700 contracts, 328 authorities hold the contracts and 182 of them hold only one, while the 10 largest investors own more than half of the contracts.

That asymmetry was written into the grant too. A government that lets each hospital trust negotiate alone against an investor holding dozens of contracts has given away the one advantage it had, which is scale.

The remedy at expiry is known and cheap beside the alternative. The IPA puts adequate preparation at seven years before the end, with an asset condition survey at least five years out, because an authority that misses the handback standard pays twice, once through the charge and again to repair what it was already paying for.

I have sat on the other side of this table, as chief financial officer of a healthcare group that sold its buildings and leased them back, and the lesson is the same from either chair. The lease, not the headline price, decides who carries the risk, and everything that happens in year 20 was written in year one.

None of this is a case against private finance. The Gulf is building its water and power on contracts of 25 years or longer with private capital today, and the countries that learn from PFI's grant will get the buildings without the hangover.

The takeaway

Three questions for a board

  1. 1Has the business case priced the works with and without private finance, and who audited the comparison?
  2. 2What does a change to the service cost under this contract, and who decides?
  3. 3When does preparation for expiry begin, and who holds the asset condition survey?

Kashif

I write on governance, capital and reform in healthcare, water and infrastructure, for boards and investors.

The views are my own and not those of any past or current employer.